Acoustic wall retrofit · ROOM phone booth
Build plan, drawings, parts list, costs and build time for a removable × mm white slat panel. Prototype 1, version , .
Open the 3D step-by-step manual →
verified measured on site or read from a product page snippet price seen only in a search result estimate must be checked before you rely on it
1 · Design
One white slat panel, cut into A ( × ) and B ( × ), slats vertical. Two black anodised angles (20 × 20 × 1 mm) wrap the bottom and top edges. Two flat aluminium bars (20 × 2 mm) cross the back in between. Every screw goes in from behind, through a PETG bushing set in the felt, into the back of a slat, so no screw shows. The panel stands on two printed feet. Four printed clips, each with five embedded Ø5 × 3 N42 magnets, hold its top against the wall leg of the steel desk bracket. Rubber pads on the back rest against the old felt. Nothing is drilled into the booth.
- Thin. The face stands mm off the old felt: a mm pad, 2 mm of aluminium, 9 mm of felt and 9 mm of slat.
- Frame barely visible. From the front you see only the 1 mm black edges of the angles at the top and bottom. The angles also hide both crosscut ends, so only the two ripped side edges need paint.
- The floor carries the weight. The slats stand on the bottom angle, which sits on the two feet. The screws hold the frame together; they don't carry the panel.
- The magnets only hold the top back. They face the bracket's wall leg and pull straight toward the wall. Three conditions: the steel must reach at least mm below the desk at each clip, no screw head may sit under a clip, and the steel must be clean (§8).
Changed in version 2.2, after a full review.
- Frame screws are now pan-head. The countersunk screws in v2.1 could not sink into a 1 mm angle. Their heads stood proud, so they reached about 3.3 mm into the slat, not the 5 mm the plan stated.
- New foot: M8 × 16 bolt in a 16 mm block. In v2.1 the bolt tip sat 0.7 mm under the angle, so the feet could raise the panel but not lower it.
- Both bars are drilled as one stack. v2.1 told you to copy one bar from the other, but its two hole patterns were different. Now the upper bar is the lower bar turned end for end.
- The steel must reach mm below the desk, not 10. The magnets reach 9.5 mm down, so 10 left no margin.
- All clearance holes are Ø4. A Ø3.6 bit is not in a normal drill set.
- New step 3: measure the delivered panel and the pads before printing. The plan and the 3D manual now use the same step numbers and the same texts.
- One parts list. The bill of materials and the cost table are computed from the same rows.
Not yet measured. Four inputs are still assumptions: (1) the height of the steel under the desk at the wall (≈); (2) the bracket itself, taken as 1 mm iron with a flat leg on the wall, how far down that leg reaches and where its screws are; (3) where the floor air inlets are; (4) the slat, felt and pad thickness of the goods you actually receive. §15 says how to check each one. Steps 2 and 3 are the two gates before anything is cut or printed.
2 · Known vs assumed
3 · Drawings
All dimensions in mm. x runs across the wall from its centre, y up from the booth floor, z out from the old felt surface.
A · Front view, installed. Slats vertical. The seam between A and B falls in a normal 13 mm gap. The clips (M) and feet (F) sit in the dark gaps above and below the panel.
B · Rear view, seen from the wall, so A is on the right. White dots: screws through the angles, one per slat. Black dots: screws through the bars. Grey dots: the 12 countersunk screws through the feet and clips. Rings: rubber pads.
C · Side view through a foot and a clip (x = −360).
D1 · Bottom corner, section through a foot screw (x = −380), scale 3:1. The slats stand on the angle; the angle sits on the foot.
D2 · Top corner, section through the middle magnet of a clip, scale 3:1. The slat lies behind the section plane and is drawn light. The clip makes the top stand mm further out than the pads do.
E · Exploded side view, layers pulled apart toward the wall. Blue dashes are screw lines. Of the 74 screws, 62 are pan-head and 12 countersunk.
4 · Cutting plan (one 2600 × 600 panel)
Face up on foam. Each piece keeps one factory end. The long cuts run along a slat, mm in from its outer face. Kerf 2.2 mm.
Remnants: the 556 × 600 piece and the 254 × 1020 strip are where you test screws and bushings (step 10). The strip cannot replace a spoiled B: B needs 9 slats and the strip has 6.
Width rule (if the smallest width is not 950)
Panel width = smallest wall width − 9. Take the difference equally off both outer slats. The slat centres, and so the positions of the feet, clips and pads, stay where they are.
Outside 944–956 the slat count changes and this plan does not apply as written.
Height rule
Panel height = height of the steel under the desk − . The is the mm floor gap, 1 + 1 for the two angle walls, the 10 mm the clips stand above the top angle, and 2 mm of air. At ≈ that gives . The feet can then move the panel about 2.5 mm down or 5 mm up (§8).
5 · Aluminium cutting list and drilling
Stock: one black anodised angle 20 × 20 × 1 mm, 2 m long, and two raw flat bars 20 × 2 mm, 1 m long. On each angle one leg lies on the back of the panel (the back leg, drilled) and the other wraps the cut end (the end leg, not drilled).
These positions come from the nominal 40 mm pitch. If your panel's 14 pitches do not measure 560, mark the holes from the slat lines on the panel instead (step 7) and use this table only as a check.
6 · Frame check
- Weight. Each slat stands on the end leg of the bottom angle. Between the feet, 720 mm apart, the angle on its own would sag about 2 mm under the whole panel estimate (simply supported, I = 1550 mm⁴). Screwed to 24 slats that are also held by the top angle and both bars it should sag much less, but I have not calculated the assembly. Check it: after step 11, stand the panel on its feet and sight along the bottom angle. If the middle hangs more than 1 mm, print a third foot and fit it at x = 0.
- Pushes. A knee or a bag pushes the panel toward the wall. The pads are at most 240 mm apart along each bar. They compress until the screw heads, which stand mm short of the old felt, touch it. So at the bars and angles the face can give about 1.5 mm estimate. Between them, a slat spans 330 mm and can bend further. I have not calculated that: push-test the prototype there.
- What the flat bars do. They hold A and B together, keep the seam closed and the slats in line. They add almost no stiffness of their own (I = 13 mm⁴). That suits a panel that leans on a wall. It would not suit a free-standing one.
- Pulls. Only the magnets at the top and the friction of the two rubber feet at the bottom resist a pull into the room. A foot hooked under the bottom edge can drag it forward. I accepted this for a panel under a desk.
7 · Screws into 9 mm slats
D3 · The three screw joints, scale 4:1. Wall on the left, room on the right. The two numbers under each joint are the millimetres of screw in the slat and the MDF left in front of its tip.
- Rule: aluminium + bushing = mm at every screw. Under the 1 mm angles the bushing is felt + 1 ( mm). That lifts the angle 1 mm off the felt, so its 20 mm end leg ends flush with the slat faces. Under the 2 mm bars the bushing is level with the felt ( mm).
- Frame screws: pan head, 3.5 × 16. A pan-head screw is measured under its head, so it reaches 16 − = mm into the slat and leaves mm of MDF in front of its tip. Don't use countersunk screws here: in a 1 mm angle the head stands proud and the screw reaches only about 3.3 mm.
- Feet and clips: countersunk, 3.5 × 20. Here the heads must finish flush, because the foot tab and the clip touch the wall. The printed parts have the countersinks.
- Pilot hole: Ø2.5 for the sheet-metal-thread screw in the parts list (Ø2.0 for a chipboard-thread screw), with a drill stop mm from the aluminium face. That stops 5 mm short of the slat face.
- Bushing: PETG, Ø10, bore Ø, in a hollow-punched Ø10 hole down to the MDF. A dab of MS polymer on its base stops it turning.
- Is 5 mm enough? The frame screws carry no weight. The largest load on any screw is the pull on one clip, about N shared by two screws. I expect a 3.5 mm screw with 5 mm in MDF to hold many times that, but I have no test value for this panel estimate. Step 10 starts with three test screws in the remnant: they must grip, and nothing may show on the slat face.
- Different panel? The bushings follow the felt, so pan-head screw length = felt + slat − 2. For 9 mm felt and 12 mm slats that is 3.5 × 19 or 20.
8 · Printed parts and magnets
Load paths. Weight: slats → bottom angle → two F feet → M8 bolts → rubber pads → booth floor. Pushes: rubber pads → old felt and wall. A pull on the top: top angle → two screws per clip → four M clips → magnets on the bracket's wall leg.
Are four clips enough?
For a panel that stands on its own feet, yes: the top only has to resist a tug. A pull at the middle of the top edge meets all magnets at once. A pull at one corner peels the clips off one at a time, and that is how the panel comes out. A gap is what would make it too weak: paint lumps or felt fluff on the steel, a screw head under a clip, or steel that ends above the magnets. Test every clip position with the spare clip in step 12: pulled straight off with a luggage scale it should take more than 1 kg. If one is weak, move it one slat sideways or fit the spare in the middle.
Printing
- Material: black PETG. ASA works too. 0.4 mm nozzle, 0.2 mm layers, 4 walls, 5 top and bottom layers, 40% gyroid; bushings 100%.
- Foot: print it on its side, with the L-shaped profile flat on the bed, so the layers run unbroken from the block into the tab. The M8 hole then prints horizontally: model it Ø9 and clean it with a drill. Press the nyloc nut into its pocket in a vice, or pull it in with the bolt.
- Clip: print it flat, wall side down, so the 0.2 mm skin over the magnets is the first layer and the countersinks open onto the bed.
- Embedding the magnets: add a pause before the first layer that closes the pockets (z = 3.4 mm). Slicers differ on whether a pause runs before or after the layer you name, so check in the preview that the pockets are still open at the pause. Put a small drop of superglue in each pocket and drop a magnet in. Either pole can face the wall; steel attracts both. Resume: two layers close the pockets. Keep the bed at 70 °C or below, because N42 magnets start to lose strength above 80 °C.
- Test first. Print one clip before the other four and check that the nozzle clears the magnets and that the clip snaps onto steel. Print a small coupon with the nut pocket and one bushing too, and try them with the real nut and screw: printers differ by a few tenths.
- Bushings: standing upright. Print the tall and the short ones as separate jobs and bag them.
- Print time: about 5 h for one booth (about 110 g) estimate: bushings 3 h, feet 1.5 h, five clips 50 min. Stay near the printer for the pause.
9 · Bill of materials (one booth)
Prices include 21% VAT. Read on 29–30 Oct 2026, except the pan-head screws (12 Nov 2026). Gamma.nl blocks automated reading, so no Gamma price is verified. The cutting base (foam board or scrap boards) is listed under tools and not counted here.
11 · Build time (one booth)
12 · Assembly procedure
The same steps as the 3D manual, with the same numbers. The manual animates each one.
13 · Costs and scaling
14 · Risks and limits
15 · Checklist before ordering