Acoustic wall retrofit · ROOM phone booth

Build plan, drawings, parts list, costs and build time for a removable × mm white slat panel. Prototype 1, version , .

Open the 3D step-by-step manual →

verified measured on site or read from a product page   snippet price seen only in a search result   estimate must be checked before you rely on it

1 · Design

One white slat panel, cut into A ( × ) and B ( × ), slats vertical. Two black anodised angles (20 × 20 × 1 mm) wrap the bottom and top edges. Two flat aluminium bars (20 × 2 mm) cross the back in between. Every screw goes in from behind, through a PETG bushing set in the felt, into the back of a slat, so no screw shows. The panel stands on two printed feet. Four printed clips, each with five embedded Ø5 × 3 N42 magnets, hold its top against the wall leg of the steel desk bracket. Rubber pads on the back rest against the old felt. Nothing is drilled into the booth.

Changed in version 2.2, after a full review.
  1. Frame screws are now pan-head. The countersunk screws in v2.1 could not sink into a 1 mm angle. Their heads stood proud, so they reached about 3.3 mm into the slat, not the 5 mm the plan stated.
  2. New foot: M8 × 16 bolt in a 16 mm block. In v2.1 the bolt tip sat 0.7 mm under the angle, so the feet could raise the panel but not lower it.
  3. Both bars are drilled as one stack. v2.1 told you to copy one bar from the other, but its two hole patterns were different. Now the upper bar is the lower bar turned end for end.
  4. The steel must reach mm below the desk, not 10. The magnets reach 9.5 mm down, so 10 left no margin.
  5. All clearance holes are Ø4. A Ø3.6 bit is not in a normal drill set.
  6. New step 3: measure the delivered panel and the pads before printing. The plan and the 3D manual now use the same step numbers and the same texts.
  7. One parts list. The bill of materials and the cost table are computed from the same rows.
Not yet measured. Four inputs are still assumptions: (1) the height of the steel under the desk at the wall (≈); (2) the bracket itself, taken as 1 mm iron with a flat leg on the wall, how far down that leg reaches and where its screws are; (3) where the floor air inlets are; (4) the slat, felt and pad thickness of the goods you actually receive. §15 says how to check each one. Steps 2 and 3 are the two gates before anything is cut or printed.

2 · Known vs assumed

3 · Drawings

All dimensions in mm. x runs across the wall from its centre, y up from the booth floor, z out from the old felt surface.

A · Front view, installed. Slats vertical. The seam between A and B falls in a normal 13 mm gap. The clips (M) and feet (F) sit in the dark gaps above and below the panel.
B · Rear view, seen from the wall, so A is on the right. White dots: screws through the angles, one per slat. Black dots: screws through the bars. Grey dots: the 12 countersunk screws through the feet and clips. Rings: rubber pads.
C · Side view through a foot and a clip (x = −360).
D1 · Bottom corner, section through a foot screw (x = −380), scale 3:1. The slats stand on the angle; the angle sits on the foot.
D2 · Top corner, section through the middle magnet of a clip, scale 3:1. The slat lies behind the section plane and is drawn light. The clip makes the top stand mm further out than the pads do.
E · Exploded side view, layers pulled apart toward the wall. Blue dashes are screw lines. Of the 74 screws, 62 are pan-head and 12 countersunk.

4 · Cutting plan (one 2600 × 600 panel)

Face up on foam. Each piece keeps one factory end. The long cuts run along a slat, mm in from its outer face. Kerf 2.2 mm.

Remnants: the 556 × 600 piece and the 254 × 1020 strip are where you test screws and bushings (step 10). The strip cannot replace a spoiled B: B needs 9 slats and the strip has 6.

Width rule (if the smallest width is not 950)

Panel width = smallest wall width − 9. Take the difference equally off both outer slats. The slat centres, and so the positions of the feet, clips and pads, stay where they are.

Outside 944–956 the slat count changes and this plan does not apply as written.

Height rule

Panel height = height of the steel under the desk − . The is the mm floor gap, 1 + 1 for the two angle walls, the 10 mm the clips stand above the top angle, and 2 mm of air. At ≈ that gives . The feet can then move the panel about 2.5 mm down or 5 mm up (§8).

5 · Aluminium cutting list and drilling

Stock: one black anodised angle 20 × 20 × 1 mm, 2 m long, and two raw flat bars 20 × 2 mm, 1 m long. On each angle one leg lies on the back of the panel (the back leg, drilled) and the other wraps the cut end (the end leg, not drilled).

These positions come from the nominal 40 mm pitch. If your panel's 14 pitches do not measure 560, mark the holes from the slat lines on the panel instead (step 7) and use this table only as a check.

6 · Frame check

7 · Screws into 9 mm slats

D3 · The three screw joints, scale 4:1. Wall on the left, room on the right. The two numbers under each joint are the millimetres of screw in the slat and the MDF left in front of its tip.

8 · Printed parts and magnets

Load paths. Weight: slats → bottom angle → two F feet → M8 bolts → rubber pads → booth floor. Pushes: rubber pads → old felt and wall. A pull on the top: top angle → two screws per clip → four M clips → magnets on the bracket's wall leg.

Are four clips enough?

For a panel that stands on its own feet, yes: the top only has to resist a tug. A pull at the middle of the top edge meets all magnets at once. A pull at one corner peels the clips off one at a time, and that is how the panel comes out. A gap is what would make it too weak: paint lumps or felt fluff on the steel, a screw head under a clip, or steel that ends above the magnets. Test every clip position with the spare clip in step 12: pulled straight off with a luggage scale it should take more than 1 kg. If one is weak, move it one slat sideways or fit the spare in the middle.

Printing

9 · Bill of materials (one booth)

Prices include 21% VAT. Read on 29–30 Oct 2026, except the pan-head screws (12 Nov 2026). Gamma.nl blocks automated reading, so no Gamma price is verified. The cutting base (foam board or scrap boards) is listed under tools and not counted here.

10 · Tools

11 · Build time (one booth)

12 · Assembly procedure

The same steps as the 3D manual, with the same numbers. The manual animates each one.

    13 · Costs and scaling

    14 · Risks and limits

    15 · Checklist before ordering

    Open the 3D step-by-step manual →